Capitol Metro makes progress on Red Line, still no opening date
Capitol Metro makes progress on Red Line, still no opening date
Monday, 22 June 2009
In a press release, Capital Metro stated it has made significant progress on the MetroRail project since last month’s report and is much closer to announcing a new opening date for the Red Line.
Here is a report on its progress:
Milestones completed since May 13
The Centralized Traffic Control signal system is in full operation and rail dispatchers are utilizing it to direct train operations. The signal system, including new work added to the original scope of the project is complete and final crossing adjustments are underway. The installation of traffic signal preemption equipment at several crossings adjacent to intersections is complete and final adjustments are underway. All MetroRail, freight and Austin Steam Train engineers and supervisors are now certified on the use of the CTC signal system. MetroRail trains have begun operating under full-service conditions in the morning to meet the timelines and stops according to the proposed service schedule without passengers.
Also, MetroRail engineers have begun comprehensive contingency training to prepare and train for unforeseen challenges.
Remaining milestones
- Complete adjustments to crossings and complete final testing for full-service operation
- Complete full-service test runs to finalize schedules
- Complete engineer contingency training
When will service begin?
Capital Metro will announce an opening date when the entire rail system is demonstrated to be operating in a consistent, reliable and safe manner. Capitol Metro will report back to the community in mid-July, if not before.
Site tools
Cedar Park | Leander Calendar
| « | < | March 2010 | > | » |
| S | M | T | W | T | F | S |
| 28 | 1 | 2 | 3 | 4 | 5 | 6 |
| 7 | 8 | 9 | 10 | 11 | 12 | 13 |
| 14 | 15 | 16 | 17 | 18 | 19 | 20 |
| 21 | 22 | 23 | 24 | 25 | 26 | 27 |
| 28 | 29 | 30 | 31 | 1 | 2 | 3 |